Case Study: Custom Pro Club Men Pullover Hoodie for an Independent Fashion Designer in Chile
Pro Club Men Pullover Hoodie for an Independent Fashion Designer in Chile
An Independent Fashion Designer approached us with a pro club men pullover hoodie requirement for Chile. The brief was specific: a defined look, a hard launch date and a unit cost that had to survive shipping and duty. This case study records what was specified, what went wrong in sampling and how the bulk order was delivered.
The challenge
- Suppliers who disappear once the deposit is paid
- Minimum order quantities far above what a growing brand can absorb
- Inconsistent sizing between production runs

What we specified
| Product | Pro Club Men Pullover Hoodie |
|---|---|
| Client type | An Independent Fashion Designer |
| Market | Chile |
| Order volume | 1,200 pieces across 3 colourways |
| Base fabric | Spandex |
| Decoration | Tonal Embroidery |
| Size range | Custom grading |
| Sampling rounds | 3 |
| Delivery window | 6 weeks from PO to ex-factory |
How it was resolved
- We rebuilt the tech pack around Spandex and locked shrinkage allowance before grading.
- Decoration was moved to Tonal Embroidery after strike-off tests showed better wash durability.
- A pre-production sample was approved and retained as the golden reference.
- Production ran with in-line inspection and a mid-run photo report.
- Cartons were packed to the client's own barcode and size ratio specification.

Result
- 1,200 pieces delivered inside the 6-week window.
- Unit cost held within 2.0% of the original quotation.
- Return rate linked to fit or workmanship stayed under 0.5%.
- The specification is now on file, so reorders reproduce the approved sample.
What we would repeat
Keep one process owner on both sides. Most delays come from hand-offs, not from machines.

Planning something similar?
Send us your tech pack or even a rough sketch — we will come back with fabric options, a costed sample plan and a realistic production calendar.